Matters need to pay attention to when EPS power replacement
The EPS power system mainly includes a rectifier charger, a battery pack, an inverter, an interpolation device, and a system controller. The EPS power supply is good, it can be used to power the power when it is critical, and the battery is an important core issue. Therefore, the battery is replaced in time after the battery is used.
First, the battery selection requirements:
1. The brand of the battery cannot be lowered. The newly replaced battery quality should be higher than the original battery quality, because there is now a lot of battles on the market, the quality is also different, the life of the life is different, and the price between the batteries is very different;
2, the amount of time of the new battery cannot be changed, the shape size should not be more than the original battery.
3. The battery capacity of the emergency power distribution cabinet is not reduced. In the design before construction, the size of its capacity is based on the theoretical data required by the owner. After the project is well-established, according to the current actual demand capacity, there may be some big wealth in the capacity of the emergency power distribution cabinet, if Reducing the battery capacity will increase trouble for future work.
4. The brand of the battery cannot be lowered. Because now there is a lot of battles in the market, the quality is also different, and the life of life is also different;
5, battery temperature detection. Check the battery surface temperature and check the battery. * Good to touch the temperature of the battery, prevent accidents that may have exploded during testing.
6, battery internal resistance detection. For each battery, the battery is detected, the unqualified battery is replaced, the battery needs is different, the internal resistance is different, the larger the time, the larger the internal resistance, the same power supply cabinet The internal battery is about ¡À 3%. If the internal resistance is large, the battery will be easily heated due to the unevenness of the internal resistance, and the battery is easily drummed.
7, battery installation. The battery installation includes the removal of the old battery, and the old battery should be safe and reasonable after the old battery is removed, and the transportation is cleaned up in the future. At the time of installation, you should pay attention to the intermediate health, packing box and waste in time.
On September 16, the reporter learned from Sichuan Province to meet the Central Environmental Protection Inspector Work Leading Group, the Central Environmental Protection Insugation team transferred to Sichuan's thirty batch, thirty-one batch, thirty-two batch of letter, and has been completed 997. The Fifth Environmental Protection Inspectus of the Central Central Environmental Protection Inspector 370 pieces of the people calls to the letter of communication, and 369 were completed as of September 14, and the remaining one piece was being processed. The Fifth Environmental Protection Inspection Team of the Central Committee forwarded the thirty-first batch of people calls to 327 people, and 326 were completed as of September 15, and the remaining one were under handling. The Fifth Environmental Protection Inspectus of the Central Central Environmental Protection Inspector 32% of the people calls 307 pieces, and 302 pieces have been completed on September 15, and the remaining 5 are being processed.
Second, the test after the battery is installed:
1. Firstly, you should check whether the components of the EPS power supply are intact, such as rectifier charger, inverters, various megapons, dual power mutual investment (ATSE is self-vying) should be prominesed.
2, perform EPS power cabinet machine debugging. If the emergency power supply is a dual power input (ATSE is self-fluidized), the dual power supply portion is transmitted in the case of disconnecting the EPS power input switch and the battery switch (insurance). The main electric input switch is closed, and the ATSE should enter the main power supply mode, and the backup input switch is closed. At this time, the main electric input switch is disconnected, and the ATSE should be able to switch to a backup power supply. After the main electric input switch is closed, the ATSE should be able to automatically restore the main electric power supply, and the status indicator of the device during this process should work. After determining that the ATSE is working properly, the EPS input switch and the battery switch (insurance) are closed. After the input voltage and charging current are normal, the load switch is sequentially closed, and the three-phase current is measured, and the primary power-on process can be completed.
3, simulate switching. After the power supply of the emergency power supply, analog switching, namely, the city's electric / emergency switching to verify the emergency power supply equipment * as an important function. Analog switches can be implemented by one of the following:
First disconnect the ATSE's backup switch, and then disconnect its main input switch. At this time, the emergency power supply shall be able to switch to emergency power supply. Recovery to network power supply only needs to close the above switches, the emergency power supply should be switched to mesh power supply.
Wuxi Huizhong Weiye Electric Co., Ltd. has a large sealed lead-acid battery capacity: 2V200AH, 2V250AH, 2V300AH, 2V350AH, 2V600AH, 2V800AH, 2V1000AH, 2V1800AH, 2V2000AH, 2V2500AH, 2V2000AH, 2V2500AH, 2V3000AH, 2V4000AH.
Third, the maintenance of the battery is maintained.
Key to strengthen the maintenance work, the maintenance personnel check the EPS power cabinet battery in the inspection equipment, and the temperature is generally different from room temperature in the case of charge, and only the battery is in a state of charge, the temperature ratio of the battery The room temperature is slightly higher. The inspector must be registered in the inspection record during measuring the battery temperature. When the battery temperature occurs, it will be found in time, and the processing of replacement batteries will be made in time to prevent other problems in the battery.
Recommend:
LiFePO4 Battery Manufacturer
Energy storage battery Manufacturer
Integrated machine energy storage battery series Manufacturer
Lead lithium battery Manufacturer
Outdoor Backup Battery Manufacturer
Portable outdoor power supply Manufacturer
Power battery Manufacturer
Powerwall LiFePO4 Battery Manufacturer
Battery rack Manufacturers
Telecom LiFePO4 Battery Manufacturer
Wall mounted battery storage Manufacturer
China Lifepo4 Battery